§ 7.659. Effective date.

 This subchapter will be effective as of July 1, 1995, and continue in effect unless revised or modified by the Governor. Applications received on or after July 1, 1995, will be included in this program.

APPENDIX A
Money Back Guarantee Permit Review Program


Permit Process Steps in Calendar DaysPublic
PERMIT NAME
No./yearAdm.1 Tech2 TechDec RevTotalCom-
RevRevRevTimement*
Oil & Gas Well Drilling1,35052500300
Coal Surface Mining135760303012760
Noncoal Surface Mining39760303012760
Coal Underground Mining10760303012760
Radioactive Material License2131000130
Air Plan Approval-Minor New Source Reviews5501555555518030
Municipal and Residual Waste Processing and Composting Facilities72060303014060
Land Application of Municipal or Residual Waste1362060303014060
Municipal Waste Beneficial Use Approvals192060303014060
Municipal and Residual Waste Transfer Facilities602060303014060
Form U for Residual Waste (with approved waste acceptance plan)1,50001500150
NPDES New2152060309020060
NPDES Major Renewals802080409023060
Public Water Supply5502080503018030
Water Obstructions and Encroachment5002060252513030
Dam Safety8020100505022030


 *Public comment time is shown for information only and should not be added to total time. Public comment time is already factored into technical and decision review times.

 NOTE: •All authorizations and related processing times are for individual permits only. General permits, when applicable, are processed in less time.
•All time is shown in DEP calendar days. The time an applicant may take to prepare or modify an application is not included.