Subchapter F. BONDING AND INSURANCE REQUIREMENTS
GENERAL PROVISIONS Sec.
86.141. Scope.
86.142. Definitions.
86.143. Requirement to file a bond.
86.144. Requirement to file a certification of liability insurance.
86.145. Department responsibilities.
AMOUNT AND DURATION OF LIABILITY
86.148. Scope.
86.149. Determination of bond amount.
86.150. Minimum amount.
86.151. Period of liability.
86.152. Adjustments.
FORM, TERMS AND CONDITIONS OF
BONDS AND INSURANCE
86.155. Scope.
86.156. Form of the bond.
86.157. Special terms and conditions for surety bonds.
86.158. Special terms and conditions for collateral bonds.
86.159. Self-bonding.
86.160. Combination of bonding instruments.
86.161. Phased deposits of collateral.
86.162. Subsidence insurance in lieu of bond.
86.162a. Anthracite Deep Mine Operators Emergency Bond Fund.
86.163. [Reserved].
86.164. [Reserved].
86.165. Failure to maintain proper bond.
86.166. Replacement of bonds.
86.167. Transfer of permits.
86.168. Terms and conditions for liability insurance.
RELEASE OF BONDS
86.170. Scope.
86.171. Procedures for seeking release of bond.
86.172. Criteria for release of bond.
86.173. [Reserved].
86.174. Standards for release of bonds.
86.175. Schedule for release of bonds.
BOND FORFEITURE
86.180. Scope.
86.181. General.
86.182. Procedures.
86.183. [Reserved].
86.184. [Reserved].
86.185. Preservation of remedies.
86.186. Scope.
86.187. Use of money.
86.188. Evaluation of bond forfeiture sites.
86.189. Reclamation of bond forfeiture sites.
86.190. Sites where reclamation is unreasonable, unnecessary or impossible; excess funds.
Cross References This subchapter cited in 25 Pa. Code § 86.34 (relating to informal conferences); 25 Pa. Code § 86.36 (relating to review of permit applications); 25 Pa. Code § 86.37 (relating to criteria for permit approval or denial); 25 Pa. Code § 86.41 (relating to conditions of permits: general and right of entry); 25 Pa. Code § 86.56 (relating to transfer of permit); 25 Pa. Code § 86.64 (relating to right of entry); 25 Pa. Code § 87.1 (relating to definitions); 25 Pa. Code § 87.65 (relating to maps and plans); 25 Pa. Code § 87.68 (relating to reclamation information); 25 Pa. Code § 87.83 (relating to prime farmlands); 25 Pa. Code § 87.159 (relating to postmining land use); 25 Pa. Code § 87.181 (relating to prime farmland: revegetation); 25 Pa. Code § 88.1 (relating to definitions); 25 Pa. Code § 88.129 (relating to revegetation: standards for successful revegetation); 25 Pa. Code § 88.217 (relating to vegetation: standards for successful vegetation); 25 Pa. Code § 88.221 (relating to postmining land use); 25 Pa. Code § 88.330 (relating to revegetation: standards for successful revegetation); 25 Pa. Code § 88.334 (relating to postdisposal land use); 25 Pa. Code § 88.493 (relating to minimum environmental protection performance standards); 25 Pa. Code § 89.88 (relating to postmining land use); 25 Pa. Code § 89.122 (relating to prime farmlands); 25 Pa. Code § 89.134 (relating to revegetation); 25 Pa. Code § 90.1 (relating to definitions); 25 Pa. Code § 90.33 (relating to reclamation plan); and 25 Pa. Code § 90.166 (relating to postdisposal land use).
GENERAL PROVISIONS
§ 86.141. Scope.
This subchapter sets forth the minimum requirements for bonding and insuring mining and reclamation operations.
Source The provisions of this § 86.142 adopted December 19, 1980, 10 Pa.B. 4789, effective July 31, 1982, 12 Pa.B. 2382; amended July 30, 1982, 12 Pa.B. 2473, effective July 31, 1982, 12 Pa.B. 2382; amended May 11, 1990, effective upon publication of notice in the Pennsylvania Bulletin that the amendments have been approved by the OSM; amended June 15, 1990, 20 Pa.B. 2517, effective July 27, 1991, 21 Pa.B. 3316; amended August 19, 1994, effective August 20, 1994, 24 Pa.B. 4195; amended November 14, 1997, effective November 15, 1997, 27 Pa.B. 6041. Immediately preceding text appears at serial pages (206684) to (206686).
Cross References The provisions of this § 86.143 adopted December 19, 1980, 10 Pa.B. 4789, effective July 31, 1982, 12 Pa.B. 2382; amended July 30, 1982, 12 Pa.B. 2473, effective July 31, 1982, 12 Pa.B. 2382; amended June 15, 1990, 20 Pa.B. 3383, effective July 27, 1991, 21 Pa.B. 3316. Immediately preceding text appears at serial pages (148536) to (148537).
Cross References This section cited in 25 Pa. Code § 86.17 (relating to permit and reclamation fees); 25 Pa. Code § 86.37 (relating to criteria for permit approval or denial); 25 Pa. Code § 86.162a (relating to Anthracite Deep Mine Operators Emergency Bond Fund); 25 Pa. Code § 86.281 (relating to financial guarantees to insure reclamationgeneral); and 25 Pa. Code § 86.294 (relating to uses and limitations).
§ 86.144. Requirement to file a certification of liability insurance.
Each applicant for a permit shall submit proof to the Department of liability insurance coverage for its mining and reclamation operations issued by an insurance company authorized to do business in this Commonwealth. The amount, duration, form, conditions, terms and method of proof of this insurance coverage shall conform to § 86.168 (relating to terms and conditions for liability insurance).
Source The provisions of this § 86.144 adopted December 19, 1980, 10 Pa.B. 4789, effective July 31, 1982, 12 Pa.B. 2382; amended July 30, 1982, 12 Pa.B. 2473, effective July 31, 1982, 12 Pa.B. 2382.
§ 86.145. Department responsibilities.
(a) The Department will prescribe and furnish the forms for filing bonds.
(b) The Department will prescribe terms and conditions for bonds and insurance.
(c) The Department will establish bonding amount rate guidelines based on the estimated cost to the Department for completing the reclamation requirements of the permittee under the law, the regulations and the conditions of the permit considering the factors listed in § 86.149(b) (relating to determination of bond amount). The guidelines shall be reviewed and, if necessary, revised by the Department annually to reflect the current cost of reclamation to the Department. The Department may consider fees, fines or other sources of money paid by the permittee and dedicated for reclamation of defaulted permit areas in determining bonding guidelines.
(d) The Department will determine the amount of the bond required for the permit areas, including adjustments to the initial amount from time to time asland acreages in the permit area are revised, costs to the Department of reclamation change or when other relevant conditions change according to the minimum requirements of § 86.149.
(e) Bonds shall be reviewed for legality and form according to established procedures.
(f) The Department will release the permittee from his bond and insurance requirements as provided in § § 86.17086.172 (relating to scope; procedures for seeking release of bond; and criteria for release of bond).
(g) The Department will cause a bond to be forfeited as provided in § § 86.18086.182 and 86.18586.190.
Source The provisions of this § 86.145 adopted December 19, 1980, 10 Pa.B. 4789, effective July 31, 1982, 12 Pa.B. 2382; amended July 30, 1982, 12 Pa.B. 2473, effective July 31, 1982, 12 Pa.B. 2382; amended June 15, 1990, 20 Pa.B. 3383, effective July 27, 1991, 21 Pa.B. 3316. Immediately preceding text appears at serial pages (148537) to (148538).
Cross References This section cited in 25 Pa. Code § 86.17 (relating to permit and reclamation fees); and 25 Pa. Code § 86.149 (relating to determination of bond amount).
AMOUNT AND DURATION OF LIABILITY
§ 86.148. Scope.
This section and § § 86.14986.152 set forth the minimum requirements for determining the amounts and time periods of liability for bonds for mining and reclamation operations.
Source The provisions of this § 86.148 adopted December 19, 1980, 10 Pa.B. 4789, effective July 31, 1982, 12 Pa.B. 2382; amended July 30, 1982, 12 Pa.B. 2473, effective July 31, 1982, 12 Pa.B. 2382.
Cross References The provisions of this § 86.149 adopted December 19, 1980, 10 Pa.B. 4789, effective July 31, 1982, 12 Pa.B. 2382; amended July 30, 1982, 12 Pa.B. 2473, effective July 31, 1982, 12 Pa.B. 2382; amended June 15, 1990, 20 Pa.B. 3383, effective July 27, 1991, 21 Pa.B. 3316. Immediately preceding text appears at serial pages (148538) to (148540).
Notes of Decisions Uniform Bond
It is clear that determinations of the amounts of bonds are to be made on a case-by-case basis, with consideration of the relevant factors contained within the Departments regulations. The use of a uniform bond of $10,000, therefore, is not appropriate. People United To Save Homes v. Department of Environmental Protection, 789 A.2d 319 (Pa. Cmwlth. 2001).
Cross References This section cited in 25 Pa. Code § 86.17 (relating to permit and reclamation fees); 25 Pa. Code § 86.145 (relating to Department responsibilities); 25 Pa. Code § 86.148 (relating to scope); and 25 Pa. Code § 86.161 (relating to phased deposits of collateral).
§ 86.150. Minimum amount.
(a) The minimum amount of bond for bituminous coal mining activities and anthracite and bituminous coal refuse disposal operations shall be $10,000 for the entire permit area, including additional acreage permit revisions thereto.
(b) The minimum amount of bond for anthracite coal mining activitiesexcept anthracite coal refuse disposal operationsis $5,000 for the entire permit area, including additional acreage permit revisions.
Source The provisions of this § 86.150 adopted December 19, 1980, 10 Pa.B. 4789, effective July 31, 1982, 12 Pa.B. 2382; amended July 30, 1982, 12 Pa.B. 2473, effective July 31, 1982, 12 Pa.B. 2382; amended June 15, 1990, 20 Pa.B. 3383, effective July 27, 1991, 21 Pa.B. 3316. Immediately preceding text appears at serial page (148540).
Cross References The provisions of this § 86.151 amended under section 7 of The Bituminous Mine Subsidence and Land Conservation Act (BMSLCA) (52 P. S. § 1406.7); section 5 of The Clean Streams Law (52 P. S. § 691.5); section 4.2 of the Surface Mining Conservation and Reclamation Act (52 P. S. § 1396.4b); section 3.2 of the Coal Refuse Disposal Control Act (52 P. S. § 30.53b); and section 1920-A of The Administrative Code of 1929 (71 P. S. § 510-20).
Source The provisions of this § 86.151 adopted December 19, 1980, 10 Pa.B. 4789, effective July 31, 1982, 12 Pa.B. 2382; amended July 30, 1982, 12 Pa.B. 2473, effective July 31, 1982, 12 Pa.B. 2382; amended June 25, 1993, effective June 26, 1993, 23 Pa.B. 3075; amended November 14, 1997, effective November 15, 1997, 27 Pa.B. 6041; amended October 21, 2005, effective October 22, 2005, 35 Pa.B. 5775. Immediately preceding text appears at serial pages (313518) and (238935) to (238936).
Cross References This section cited in 25 Pa. Code § 86.148 (relating to scope); 25 Pa. Code § 86.159 (relating to self-bonding); 25 Pa. Code § 86.161 (relating to phased deposits of collateral); 25 Pa. Code § 86.174 (relating to standards for release of bonds); 25 Pa. Code § 86.175 (relating to schedule for release of bond); 25 Pa. Code § 87.155 (relating to revegetation: standards for successful revegetation); 25 Pa. Code § 87.156 (relating to revegetation: techniques and frequency of measurement); 25 Pa. Code § 87.209 (relating to criteria and schedule for release of bonds on pollution abatement areas); 25 Pa. Code § 88.129 (relating to revegetation: standards for successful revegetation); 25 Pa. Code § 88.217 (relating to vegetation: standards for successful vegetation); 25 Pa. Code § 88.330 (relating to revegetation: standards for successful revegetation); 25 Pa. Code § 88.509 (relating to criteria and schedule for release of bonds on pollution abatement areas); and 25 Pa. Code § 89.86 (relating to revegetation).
§ 86.152. Bond adjustments.
(a) The amount of bond required and the terms of the acceptance of the applicants bond will be adjusted by the Department from time to time as the area requiring bond coverage is increased or decreased, or when the cost of future reclamation changes, or when the projected subsidence damage repair liability changes. The Department may specify periodic times or set a schedule for reevaluating and adjusting the bond amount to fulfill this requirement. This requirement shall only be binding upon the permittee and does not compel a third party, including surety companies, to provide additional bond coverage and does not extend the coverage of a subsidence bond beyond the requirements imposed by sections 5, 5.4, 5.5 and 5.6 of the Bituminous Mine Subsidence and Land Conservation Act.
(b) A permittee may request reduction of the required bond amount upon submission of evidence to the Department that warrants a reduction of the bond amount by proving that the permittees method of operation or other circumstances will reduce the maximum estimated cost to the Department to complete the reclamation, restoration or abatement responsibilities.
(c) Bond adjustments which involve unaffected portions of a permit area upon which no reclamation liability has been incurred or permits that have not been activated and upon which no reclamation liability has been incurred, and bond adjustments which are based on revisions of the cost estimates of reclamation, are not subject to the procedures of § § 86.17086.172 (relating to scope; procedures for seeking release of bond; and criteria for release of bond), except as provided in § 86.172(b) and (c).
(d) The Department will notify the permittee, the surety and any person with a property interest in collateral who has requested the notification, of any proposed adjustment to the bond amount. The Department will also provide the permittee an opportunity for an informal conference on the adjustment.
Authority The provisions of this § 86.152 amended under the authority of section 7 of The Bituminous Mine Subsidence and Land Conservation Act (BMSLCA) (52 P. S. § 1406.7); section 5 of The Clean Streams Law (35 P. S. § 691.5); section 4.2 of the Surface Mining Conservation and Reclamation Act (52 P. S. § 1396.4b); section 3.2 of the Coal Refuse Disposal Control Act (52 P. S. § 30.53b); and section 1920-A of The Administrative Code of 1929 (71 P. S. § 510-20).
Source The provisions of this § 86.152 adopted December 19, 1980, 10 Pa.B. 4789, effective July 31, 1982, 12 Pa.B. 2382; amended July 30, 1982, 12 Pa.B. 2473, effective July 31, 1982, 12 Pa.B. 2382; amended June 15, 1990, 20 Pa.B. 3383, effective July 27, 1991, 21 Pa.B. 3316; amended November 14, 1997, effective November 15, 1997, 27 Pa.B. 6041; amended November 28, 1997, effective November 29, 1997, 27 Pa.B. 6186; amended October 21, 2005, effective October 22, 2005, 35 Pa.B. 5775. Immediately preceding text appears at serial pages (238936) to (238937).
Cross References This section cited in 25 Pa. Code § 86.148 (relating to scope); 25 Pa. Code § 86.151 (relating to period of liability); 25 Pa. Code § 86.161 (relating to phased deposits of collateral); and 25 Pa. Code § 86.165 (relating to failure to maintain proper bond).
FORM, TERMS AND CONDITIONS OF BONDS AND INSURANCE
§ 86.155. Scope.
This section and § § 86.15686.162a and 86.16586.168 establish the minimum standards for the form of the bond for mining and reclamation activities, and the terms and conditions applicable to bonds and liability insurance.
Source The provisions of this § 86.155 adopted December 19, 1980, 10 Pa.B. 4789, effective July 31, 1982, 12 Pa.B. 2382; amended July 30, 1982, 12 Pa.B. 2473, effective July 31, 1982, 12 Pa.B. 2382.
§ 86.156. Form of the bond.
(a) The Department will accept the following types of bonds:
(1) A surety bond.
(2) A collateral bond.
(3) A self bond.
(4) A combination of bonding instruments as provided in § 86.160 (relating to combination of bonding instruments), for coal surface mining activities.
(5) A phased deposit of collateral bond as provided in § 86.161 (relating to phased deposits of collateral), for long-term mines, long-term facilities and coal refuse disposal activities.
(6) Subsidence insurance as provided in § 86.162 (relating to subsidence insurance in lieu of bond), for risk of subsidence from bituminous underground mines.
(b) A financial or other institution which issues or provides annuities, trust funds, letters of credit, certificates of deposit, life or property and casualty insurance or surety bonds, shall certify in writing to the Department that it will immediately notify the Department and the permittee, if permissible under the law, of any action filed either alleging the insolvency or bankruptcy of the institution, or permittee or alleging violations which would result in suspension or revocation of its charter or license to do business in this Commonwealth.
(c) A permittee executing a bond shall certify in writing to the Department that it will immediately notify the Department, if permissible under the law, of action filed alleging the insolvency or bankruptcy of the permittee.
Authority The provisions of this § 86.156 amended under the Surface Mining Conservation and Reclamation Act (52 P. S. § § 1396.11396.19a); the Bituminous Mine Subsidence and Land Conservation Act (52 P. S. § § 1406.11406.21); The Clean Streams Law (35 P. S. § § 691.1691.1001); and section 1920-A of The Administrative Code of 1929 (71 P. S. § 510-20).
Source The provisions of this § 86.156 adopted December 19, 1980, 10 Pa.B. 4789, effective July 31, 1982, 12 Pa.B. 2382; amended July 30, 1982, 12 Pa.B. 2473, effective July 31, 1982, 12 Pa.B. 2382; amended June 15, 1990, 20 Pa.B. 3383, effective July 27, 1991, 21 Pa.B. 3316; amended December 15, 1995, effective December 16, 1995, 25 Pa.B. 5821; amended November 14, 1997, effective November 15, 1997, 27 Pa.B. 6041; amended November 28, 1997, effective November 29, 1997, 27 Pa.B. 6186. Immediately preceding text appears at serial pages (237095) to (237096).
Cross References The provisions of this § 86.157 adopted December 19, 1980, 10 Pa.B. 4789, effective July 31, 1982, 12 Pa.B. 2382; amended July 30, 1982, 12 Pa.B. 2473, effective July 31, 1982, 12 Pa.B. 2382; amended June 15, 1990, 20 Pa.B. 3383, effective July 27, 1991, 21 Pa.B. 3316; amended November 14, 1997, effective November 15, 1997, 27 Pa.B. 6041. Immediately preceding text appears at serial pages (206693) to (206694).
Cross References The provisions of this § 86.158 adopted December 19, 1980, 10 Pa.B. 4789, effective July 31, 1982, 12 Pa.B. 2382; amended July 30, 1982, 12 Pa.B. 2473, effective July 31, 1982, 12 Pa.B. 2382; amended June 15, 1990, 20 Pa.B. 3383, effective July 27, 1991, 21 Pa.B. 3316; amended November 14, 1997, effective November 15, 1997, 27 Pa.B. 6041. Immediately preceding text appears at serial pages (206695) to (206697).
Cross References The provisions of this § 86.159 adopted December 19, 1980, 10 Pa.B. 4789, effective July 31, 1982, 12 Pa.B. 2382; amended July 30, 1982, 12 Pa.B. 2473, effective July 31, 1982, 12 Pa.B. 2382; amended May 11, 1990, effective upon publication of notice in the Pennsylvania Bulletin that the amendments have been approved by the OSM, 20 Pa.B. 2517; amended August 19, 1994, effective August 20, 1994, 24 Pa.B. 4195. Immediately preceding text appears at serial pages (158767) to (158775).
Cross References This section cited in 25 Pa. Code § 86.155 (relating to scope); and 25 Pa. Code § 86.282 (relating to participation requirements).
§ 86.160. Combination of bonding instruments.
A permittee for a coal mining activities permit may post a combination of surety, collateral and self-bonds for the permit. A bond instrument shall be construed as part of the bond for the entire permit.
Source The provisions of this § 86.160 adopted December 19, 1980, 10 Pa.B. 4789, effective July 31, 1982, 12 Pa.B. 2382; amended July 30, 1982, 12 Pa.B. 2473, effective July 31, 1982, 12 Pa.B. 2382; amended June 15, 1990, 20 Pa.B. 3383, effective July 27, 1991, 21 Pa.B. 3316; amended November 28, 1997, effective November 29, 1997, 27 Pa.B. 6186. Immediately preceding text appears at serial pages (237107) to (237108).
Cross References The provisions of this § 86.161 adopted December 19, 1980, 10 Pa.B. 4789, effective July 31, 1982, 12 Pa.B. 2382; amended July 30, 1982, 12 Pa.B. 2473, effective July 31, 1982, 12 Pa.B. 2382; amended June 15, 1990, 20 Pa.B. 3383, effective July 27, 1991, 21 Pa.B. 3316; amended November 14, 1997, effective November 15, 1997, 27 Pa.B. 6041. Immediately preceding text appears at serial pages (219170) and (206705).
Cross References This section cited in 25 Pa. Code § 86.155 (relating to scope); 25 Pa. Code § 86.156 (relating to form of the bond); 25 Pa. Code § 86.162a (relating to Anthracite Deep Mine Operators Emergency Bond Fund); 25 Pa. Code § 86.165 (relating to failure to maintain proper bond); and 25 Pa. Code § 86.166 (relating to replacement of bonds).
§ 86.162. Subsidence insurance in lieu of bond.
A permittee for a bituminous underground mine, may, in lieu of bond coverage for the risk of subsidence, purchase and maintain in force subsidence insurance as provided by the act of August 23, 1961 (P. L. 1068, No. 484) (52 P. S. § § 32013226), entitled, An Act to provide for the creation and administration of a Coal and Clay Subsidence Insurance Fund within the Department of Environmental Resources for the insurance of compensation for damages to subscribers thereto..., for the benefit of all affected surface property owners.
Source The provisions of this § 86.162 adopted December 19, 1980, 10 Pa.B. 4789, effective July 31, 1982, 12 Pa.B. 2382; amended July 30, 1982, 12 Pa.B. 2473, effective July 31, 1982, 12 Pa.B. 2382.
Cross References The provisions of this § 86.162a adopted June 25, 1993, effective June 26, 1993, 23 Pa.B. 3075.
Cross References This section cited in 25 Pa. Code § 86.155 (relating to scope); and 25 Pa. Code § 86.165 (relating to failure to maintain proper bond).
§ 86.163. [Reserved].
Source The provisions of this § 86.163 adopted December 19, 1980, 10 Pa.B. 4789, effective July 31, 1982, 12 Pa.B. 2382; reserved July 30, 1982, 12 Pa.B. 2473, effective July 31, 1982, 12 Pa.B. 2382.
§ 86.164. [Reserved].
Source The provisions of this § 86.164 adopted December 19, 1980, 10 Pa.B. 4789, effective July 31, 1982, 12 Pa.B. 2382; reserved July 30, 1982, 12 Pa.B. 2473, effective July 31, 1982, 12 Pa.B. 2382.
§ 86.165. Failure to maintain proper bond.
(a) If a permittee fails to promptly post additional bond required under § 86.152 (relating to adjustments), or fails to make timely deposits of bond according to the schedule submitted under § 86.161 (relating to phased deposits of collateral), or fails to make payments under § 86.162a (relating to Anthracite Deep Mine Operators Emergency Bond Loan Fund) or fails to maintain subsidence insurance provided in § 86.162 (relating to subsidence insurance in lieu of bond), the Department will issue a notice of violation to the permittee, and if the permittee fails to correct the violation within 15 days of the notice, the Department will issue a cessation order for the permittees permit areas and thereafter take actions that may be appropriate.
(b) The permittee shall maintain bonds in an amount and with sufficient guarantee as required by this chapter. If a surety company who had provided surety bonds, or a bank who had provided letters of credit or certificates of deposit for a permittee, enters into bankruptcy or liquidation, or has its license suspended or revoked or for another reason indicates an inability or unwillingness to provide an adequate financial guarantee of the obligations under the bond or instrument, the Department will issue a notice of violation to the permittee requiring that affected permits be rebonded according to the requirements of this subchapter and, if the permittee fails to correct the violation within 90 days of the notice, the Department will issue a cessation order for the permittees permit areas and thereafter take appropriate action.
Source The provisions of this § 86.165 adopted December 19, 1980, 10 Pa.B. 4789, effective July 31, 1982, 12 Pa.B. 2382; amended July 30, 1982, 12 Pa.B. 2473, effective July 31, 1982, 12 Pa.B. 2382; amended June 15, 1990, 20 Pa.B. 3383, effective July 27, 1991, 21 Pa.B. 3316; amended June 25, 1993, effective June 26, 1993, 23 Pa.B. 3075. Immediately preceding text appears at serial pages (158777) to (158778).
Notes of Decisions When the Department of Environmental Resources notifies a permittee to rebond based on a liquidation of the original surety company, the permittee must exhaust their administrative remedies under 71 P. S. § 510-21 before the Environmental Hearing Board. Benjamin Coal Co. v. Department of Environmental Resources, 513 A.2d 1120 (Pa. Cmwlth. 1986).
Cross References The provisions of this § 86.166 adopted December 19, 1980, 10 Pa.B. 4789, effective July 31, 1982, 12 Pa.B. 2382; amended July 30, 1982, 12 Pa.B. 2473, effective July 31, 1982, 12 Pa.B. 2382; amended May 11, 1990, effective upon publication of notice in the Pennsylvania Bulletin that the amendments have been approved by the OSM, 20 Pa.B. 2517; amended June 15, 1990, 20 Pa.B. 3383, effective July 27, 1991, 21 Pa.B. 3316. Immediately preceding text appears at serial page (148559).
Cross References The provisions of this § 86.167 adopted December 19, 1980, 10 Pa.B. 4789, effective July 31, 1982, 12 Pa.B. 2382; amended July 30, 1982, 12 Pa.B. 2473, effective July 31, 1982, 12 Pa.B. 2382.
Cross References The provisions of this § 86.168 adopted December 19, 1980, 10 Pa.B. 4789, effective July 31, 1982, 12 Pa.B. 2382; amended July 30, 1982, 12 Pa.B. 2473, effective July 31, 1982, 12 Pa.B. 2382; amended June 15, 1990, 20 Pa.B. 3383, effective July 27, 1991, 21 Pa.B. 3316; amended November 14, 1997, effective November 15, 1997, 27 Pa.B. 6041. Immediately preceding text appears at serial pages (219171) to (219172).
Notes of Decisions Effect of Regulation
The Departments regulations impose a duty upon a permittee to obtain liability insurance that complies with the regulations. Although the regulations require all policies to contain a rider requiring the insurer to provide the Department with prior notice of intended termination of coverage, in the absence of a rider, there is no notice of requirement imposed upon the insurer. This is consistent with the legislatures objective of ensuring that mining operations are conducted with the type of insurance coverage deemed necessary. If a policy does not contain the requisite notice rider, the permit should not issue. Acceptance Ins. Co. v. Sloan, 263 F.3d 278 (3rd Cir. 2001).
Cross References This section cited in 25 Pa. Code § 86.55 (relating to permit renewals; general requirements); 25 Pa. Code § 86.67 (relating to personal injury and property damage insurance information); 25 Pa. Code § 86.144 (relating to requirement to file a certification of liability insurance); and 25 Pa. Code § 86.155 (relating to scope).
RELEASE OF BONDS
§ 86.170. Scope.
This section and § § 86.171 and 86.172 (relating to procedures for seeking release of bond; and criteria for release of bond) set forth the procedures and criteria for release of bonds for mining and reclamation operations.
Source The provisions of this § 86.170 adopted December 19, 1980, 10 Pa.B. 4789, effective July 31, 1982, 12 Pa.B. 2382; amended July 30, 1982, 12 Pa.B. 2473, effective July 31, 1982, 12 Pa.B. 2382.
Cross References The provisions of this § 86.171 adopted December 19, 1980, 10 Pa.B. 4789, effective July 31, 1982, 12 Pa.B. 2382; amended July 30, 1982, 12 Pa.B. 2473, effective July 31, 1982, 12 Pa.B. 2382; amended January 4, 1985, effective immediately upon the approval by the Secretary of the United States Department of the Interior and publication thereof in the Pennsylvania Bulletin, 15 Pa.B. 13; amended June 15, 1990, 20 Pa.B. 3383, effective July 27, 1991, 21 Pa.B. 3316; amended November 14, 1997, effective November 15, 1997, 27 Pa.B. 6041; amended November 28, 1997, effective November 29, 1997, 27 Pa.B. 6186. Immediately preceding text appears at serial pages (237114) to (237118).
Cross References This section cited in 25 Pa. Code § 86.145 (relating to Department responsibilities); 25 Pa. Code § 86.152 (relating to adjustments); 25 Pa. Code § 86.159 (relating to self-bonding); 25 Pa. Code § 86.162a (relating to Anthracite Deep Mine Operators Emergency Bond Fund); 25 Pa. Code § 86.166 (relating to replacement of bonds); 25 Pa. Code § 86.170 (relating to scope); 25 Pa. Code § 86.175 (relating to schedule for release of bond); 25 Pa. Code § 86.182 (relating to procedures); 25 Pa. Code § 86.283 (relating to procedures); 25 Pa. Code § 86.284 (relating to forfeiture); and 25 Pa. Code § 86.294 (relating to uses and limitations).
§ 86.172. Criteria for release of bond.
(a) The Department may release all or part of a bond under § 86.175 (relating to schedule for release of bond) if it is satisfied that the entire permit area or portion of a permit area has been reclaimed to the standards in § 86.174 (relating to standards for release of bonds).
(b) The release or adjustment of a bond or portion of a bond does not relieve the operator of further reclamation liability on the permit area.
(c) The Department will not release or adjust bonds if the release or adjustment would reduce the amount of bond to less than that necessary for the Department to complete the approved reclamation plan; achieve compliance with requirements of the acts, regulations thereunder and the conditions of the permits; and abate significant environmental harm to air, water or land resources or danger to the public health and safety which may occur prior to the release of bonds from the permit area. When the permit includes an alternative postmining land use plan approval under § 87.159, § 88.133, § 88.221, § 88.334, § 88.492, § 89.88 or § 90.166, the Department will retain sufficient bond amounts for the Department to complete additional work which would be required to achieve compliance with the general standards for revegetation in § 87.155, § 88.129, § 88.217, § 88.330, § 88.492, § 89.86 or § 90.159, if the permittee fails to implement the approved alternative postmining land use plan.
Source The provisions of this § 86.172 adopted December 19, 1980, 10 Pa.B. 4789, effective July 31, 1982, 12 Pa.B. 2382; amended July 30, 1982, 12 Pa.B. 2473, effective July 31, 1982, 12 Pa.B. 2382; amended January 4, 1985, effective immediately upon the approval by the Secretary of the United States Department of the Interior and publication thereof in the Pennsylvania Bulletin, 15 Pa.B. 13; amended June 15, 1990, 20 Pa.B. 3383, effective July 27, 1991, 21 Pa.B. 3316. Immediately preceding text appears at serial pages (148564) to (148565).
Cross References This section cited in 25 Pa. Code § 86.145 (relating to Department responsibilities); 25 Pa. Code § 86.152 (relating to adjustments); 25 Pa. Code § 86.159 (relating to self-bonding); 25 Pa. Code § 86.162a (relating to Anthracite Deep Mine Operators Emergency Bond Fund); 25 Pa. Code § 86.166 (relating to replacement of bonds); 25 Pa. Code § 86.170 (relating to scope); 25 Pa. Code § 86.171 (relating to procedures for seeking release of bond); 25 Pa. Code § 86.175 (relating to schedule for release of bond); 25 Pa. Code § 86.182 (relating to procedures); 25 Pa. Code § 86.283 (relating to procedures); 25 Pa. Code § 86.284 (relating to forfeiture); 25 Pa. Code § 86.294 (relating to uses and limitations); 25 Pa. Code § 87.208 (relating to request for bond release); 25 Pa. Code § 88.508 (relating to request for bond release); and 25 Pa. Code § 90.308 (relating to request for bond release).
§ 86.173. [Reserved].
Source The provisions of this § 86.173 adopted December 19, 1980, 10 Pa.B. 4789, effective July 31, 1982, 12 Pa.B. 2382; amended July 30, 1982, 12 Pa.B. 2473, effective July 31, 1982, 12 Pa.B. 2382; reserved June 15, 1990, 20 Pa.B. 3383, effective July 27, 1991, 21 Pa.B. 3316. Immediately preceding text appears at serial page (148565).
§ 86.174. Standards for release of bonds.
(a) When the entire permit area or a portion of a permit area has been backfilled and regraded to the approximate original contour or approved alternative, and when drainage controls have been installed in accordance with the approved reclamation plan, Stage 1 reclamation standards have been met.
(b) When the entire permit area or a portion of the permit area meets the following standards, Stage 2 reclamation has been achieved:
(1) Topsoil has been replaced and revegetation has been successfully established in accordance with the approved reclamation plan.
(2) The reclaimed lands are not contributing suspended solids to stream flow or runoff outside the permit area in excess of the requirements of the acts, regulations thereunder or the permit.
(3) If prime farmlands are present, the soil productivity has been returned to the required level when compared with nonmined prime farmland in the surrounding area, to be determined from the soil survey performed under the reclamation plan approved in Chapters 8790.
(4) If a permanent impoundment has been approved as an alternative postmining land use, the plan for management of the permitted impoundment has been implemented to the satisfaction of the Department.
(c) When the entire permit area or a portion of the permit area meets the following performance standards, State 3 reclamation has been achieved:
(1) The permittee has successfully completed mining and reclamation operations in accordance with the approved reclamation plan so that the land is capable of supporting postmining land use approved under § § 87.159, 88.133, 89.88 and 90.166.
(2) The permittee has achieved compliance with the requirements of the acts, regulations thereunder, the conditions of the permit and the applicable liability period under § 86.151 (relating to period of liability) has expired.
(d) Additional standards for release of bonds for underground mining operations are as follows: release of the bond posted for mine subsidence, 10 years after completion of mining and reclamation.
Source The provisions of this § 86.174 adopted June 15, 1990, 20 Pa.B. 3383, effective July 27, 1991, 21 Pa.B. 3316; amended November 14, 1997, effective November 15, 1997, 27 Pa.B. 6041; amended May 8, 1998, effective May 9, 1998, 28 Pa.B. 2227; corrected January 16, 2004, effective May 9, 1998, 34 Pa.B. 388. Immediately preceding text appears at serial pages (281193) to (281194).
Cross References This section cited in 25 Pa. Code § 86.172 (relating to criteria for release of bond); 25 Pa. Code § 86.175 (relating to schedule for release of bond); 25 Pa. Code § 86.264 (relating to forfeiture); and 25 Pa. Code § 86.294 (relating to uses and limitations).
§ 86.175. Schedule for release of bond.
(a) The Department will not release any portion of the liability under bonds applicable to a permit area or designated phase of a permit area until it finds that the permittee has complied with § § 86.171, 86.172 and 86.174 (relating to procedures for seeking release of bond; criteria for release of bond; and standards for release of bonds).
(b) The amount of bonds applicable to a permit area or designated phase of a permit area which may be released shall be calculated on the following basis:
(1) Release of an amount not to exceed 60% of the total bond amount on the permit area or designated phase of a permit area upon completion and approval by the Department of Stage 1 reclamation.
(2) Release of an additional amount of bond on the permit area or designated phase of a permit area upon completion and approval by the Department of Stage 2 reclamation but retaining an amount of bond coverage sufficient to cover the cost of reestablishing vegetation and reconstructing drainage structures if completed by a third party and for the period specified for permit liability in § 86.151 (relating to period of liability).
(3) Release of the remaining portion of the total bond on the permit area or designated phase of a permit area after standards of Stage 3 reclamation have been attained.
Authority The provisions of this § 86.175 amended under the Surface Mining Conservation and Reclamation Act (52 P. S. § § 1396.11396.19a); the Bituminous Mine Subsidence and Land Conservation Act (52 P. S. § § 1406.11406.21); The Clean Streams Law (35 P. S. § § 691.1691.1001); and section 1920-A of The Administrative Code of 1929 (71 P. S. § 510-20).
Source The provisions of this § 86.175 adopted June 15, 1990, 20 Pa.B. 3383, effective July 27, 1991, 21 Pa.B. 3316; amended December 15, 1995, effective December 16, 1995, 25 Pa.B. 5821; amended November 14, 1997, effective November 15, 1997, 27 Pa.B. 6041. Immediately preceding text appears at serial pages (228232) to (228233).
Cross References This section cited in 25 Pa. Code § 86.172 (relating to criteria for release of bond); 25 Pa. Code § 86.284 (relating to forfeiture); and 25 Pa. Code § 86.294 (relating to uses and limitations).
BOND FORFEITURE
§ 86.180. Scope.
This section and § § 86.181, 86.182 and 86.185 (relating to general; procedures; and preservation of remedies) set forth the procedures and criteria for the forfeiture of bond as a result of the permittees failure to meet the conditions upon the bond.
Source The provisions of this § 86.180 adopted December 19, 1980, 10 Pa.B. 4789, effective July 31, 1982, 12 Pa.B. 2382; amended July 30, 1982, 12 Pa.B. 2473, effective July 31, 1982, 12 Pa.B. 2382.
Cross References This section cited in 25 Pa. Code § 86.145 (relating to Department responsibilities); 25 Pa. Code § 86.158 (relating to special terms and conditions for collateral bonds); and 25 Pa. Code § 86.188 (relating to evaluation of bond forfeiture sites).
§ 86.181. General.
(a) The Department will forfeit the bonds for a permit when it determines that:
(1) The permittee has violated and continues to violate any of the terms or conditions of the bond.
(2) The permittee has failed and continues to fail to conduct the mining or reclamation operations in accordance with the law, the regulations adopted thereunder or the conditions of the permit.
(3) The permittee has abandoned the permit area.
(4) The permits for the area under the bond have been revoked, and the permittee has failed to complete the reclamation, abatement and revegetation required by the law, the regulations adopted thereunder and the conditions of the permit.
(5) The permittee has failed to comply with a compliance schedule in an adjudicated proceeding, consent order or agreement approved by the Department.
(6) The permittee has become insolvent, failed in business, been adjudicated a bankrupt, filed a petition in bankruptcy or for a receiver, or had a receiver appointed by the court; or a creditor of the permittee has attached or executed a judgment against the permittees equipment, materials or facilities at the permit area, or on the collateral pledged to the Department; and the permittee cannot demonstrate or prove the ability to continue to operate in compliance with the acts, the regulations adopted thereunder and the conditions of the permit.
Source The provisions of this § 86.181 adopted December 19, 1980, 10 Pa.B. 4789, effective July 31, 1982, 12 Pa.B. 2382; amended July 30, 1982, 12 Pa.B. 2473, effective July 31, 1982, 12 Pa.B. 2382.
Cross References This section cited in 25 Pa. Code § 86.145 (relating to Department responsibilities); 25 Pa. Code § 86.158 (relating to special terms and conditions for collateral bonds); 25 Pa. Code § 86.180 (relating to scope); 25 Pa. Code § 86.188 (relating to evaluation of bond forfeiture sites); 25 Pa. Code § 86.281 (relating to financial guarantees to insure reclamationgeneral); 25 Pa. Code § 86.284 (relating to forfeiture); and 25 Pa. Code § 86.295 (relating to forfeiture).
§ 86.182. Procedures.
(a) The Department will send written notification by mail to the permittee, and the surety on the bond of the Departments intent to forfeit the bond and the reasons for the forfeiture.
(b) If forfeiture of the bond is required, the Department will:
(1) Send written notification by mail to the permittee, and the surety on the bond of the Departments determination to forfeit the bond and the reasons for the forfeiture.
(2) Advise the permittee and surety of their right to appeal to the EHB under section 4 of the Environmental Hearing Board Act of 1988 (35 P. S. § 7514).
(3) Notify the surety of the requirement to pay the amount of the forfeited bond over to the Department within 30 days after notice by certified mail from the Department. The money shall be held in escrow with any interest accruing to the Department pending the resolution of any appeals. If it is determined, by a court of competent jurisdiction, after exhaustion of appeals, that the Commonwealth was not entitled to all or a portion of the amount forfeited, the interest shall accrue proportionately to the surety in the amount determined to be improperly forfeited by the Department.
(4) Proceed to collect on the bond as provided by applicable laws for the collection of defaulted bonds or other debts, consistent with this section, if timely appeal is not filed or if an appeal is filed and the appeal is unsuccessful.
(c) The written determination to forfeit the bond, including the reasons for forfeiture, will be a final decision by the Department.
(d) The Department will forfeit bonds deposited for a permit area, including designated phases of a permit area and amended permit areas, except for that portion of the bond which has been released as provided in § § 86.17086.172 (relating to scope; procedures for seeking release of bond; and criteria for release of bond). Liability on every bond posted for a permit area, designated phase of a permit area, or an amendment thereof, shall cover violations within the permit area or resulting from mining of the permit area.
(e) In lieu of paying the amount of the forfeited bond within 30 days after notice, a surety may reclaim the forfeited site upon the consent and approval of the Department. The surety shall notify the Department of its intent to reclaim the site within 30 days after the notice of forfeiture. The notification shall include a time frame within which the surety will submit a proposal which describes both the reclamation work to be done and a schedule for completion of the reclamation. Subject to the Departments approval of the time frame and the subsequent reclamation proposal, the Department and the surety will enter into a consent order and agreement specifying the terms of the reclamation work to be done.
(f) If the Department declares a collateral bond forfeited, it will pay, or direct the State Treasurer to pay, the collateral funds into the Surface Mining Conservation and Reclamation Fund. If upon proper demand and presentation, the banking institution or other person or municipality which issued the collateral refuses to pay the Department the proceeds of a collateral undertaking, such as a certificate of deposit, letter of credit or government negotiable security, the Department will take appropriate steps to collect the proceeds.
(g) The Department will use funds collected from bond forfeiture to complete the reclamation plan, or remaining portion thereof, on the permit area or increment to which bond coverage applies.
(h) If the amount forfeited is:
(1) Insufficient to pay for the full cost of reclamation, the operator shall be liable for remaining costs. The Department may complete, or authorize completion of, the reclamation of the bonded area and may recover from the operator all costs of reclamation in excess of the amount forfeited.
(2) More than the amount necessary to complete the reclamation, the excess funds will be used by the Department, as approved by the Secretary, for any of the purposes provided in section 18(a) of the act (52 P. S. § 1397.18(a)).
Authority The provisions of this § 86.182 amended under the Surface Mining Conservation and Reclamation Act (52 P. S. § § 1396.11396.19a); the Bituminous Mine Subsidence and Land Conservation Act (52 P. S. § § 1406.11406.21); The Clean Streams Law (35 P. S. § § 691.1691.1001); and section 1920-A of The Administrative Code of 1929 (71 P. S. § 510-20).
Source The provisions of this § 86.182 adopted December 19, 1980, 10 Pa.B. 4789, effective July 31, 1982, 12 Pa.B. 2382; amended July 30, 1982, 12 Pa.B. 2473, effective July 31, 1982, 12 Pa.B. 2382; amended February 6, 1987, effective February 7, 1987, 17 Pa.B. 641; amended June 15, 1990, 20 Pa.B. 3383, effective July 27, 1991, 21 Pa.B. 3316; amended December 15, 1995, effective December 16, 1995, 25 Pa.B. 5821; amended November 14, 1997, effective November 15, 1997, 27 Pa.B. 6041; amended November 28, 1997, effective November 29, 1997, 27 Pa.B. 6186. Immediately preceding text appears at serial pages (237123) to (237124).
Cross References This section cited in 25 Pa. Code § 86.145 (relating to Department responsibilities); 25 Pa. Code § 86.158 (relating to special terms and conditions for collateral bonds); 25 Pa. Code § 86.180 (relating to scope); and 25 Pa. Code § 86.188 (relating to evaluation of bond facilities sites).
§ 86.183. [Reserved].
Source The provisions of this § 86.183 adopted December 19, 1980, 10 Pa.B. 4789, effective July 31, 1982, 12 Pa.B. 2382; reserved July 30, 1982, 12 Pa.B. 2473, effective July 31, 1982, 12 Pa.B. 2382.
§ 86.184. [Reserved].
Source The provisions of this § 86.184 adopted December 19, 1980, 10 Pa.B. 4789, effective July 31, 1982, 12 Pa.B. 2382; reserved July 30, 1982, 12 Pa.B. 2473, effective July 31, 1982, 12 Pa.B. 2382.
§ 86.185. Preservation of remedies.
Remedies provided in law for violation of but not limited to the Surface Mining Conservation and Reclamation Act (52 P. S. § § 1396.11396.31), The Clean Streams Law (35 P. S. § § 691.1691.1001), the Air Pollution Control Act (35 P. S. § § 40014015), the Dam Safety and Encroachments Act (32 P. S. § § 693.1693.27), the Coal Refuse Disposal Control Act (52 P. S. § § 30.5130.66), the Solid Waste Management Act (35 P. S. § § 6018.1016018.1003), and the Bituminous Mine Subsidence and Land Conservation Act (52 P. S. § § 1406.11406.21), the regulations adopted thereunder, or the conditions of the permits, are expressly preserved. Nothing in this subchapter may be construed as an exclusive penalty or remedy for the violations of law. No action taken under this subchapter may waive or impair another remedy or penalty provided in law.
Source The provisions of this § 86.185 adopted December 19, 1980, 10 Pa.B. 4789, effective July 31, 1982, 12 Pa.B. 2382; amended July 30, 1982, 12 Pa.B. 2473, effective July 31, 1982, 12 Pa.B. 2382.
Cross References This section cited in 25 Pa. Code § 86.145 (relating to Department responsibilities); 25 Pa. Code § 86.158 (relating to special terms and conditions for collateral bonds); 25 Pa. Code § 86.180 (relating to scope); and 25 Pa. Code § 86.188 (relating to evaluation of bond forfeiture sites).
§ 86.186. Scope.
Sections 86.18786.190 set forth the procedures and criteria for the use of money in the Surface Mining Conservation and Reclamation Fund. For the purposes of these sections, the term Fund means the Surface Mining Conservation and Reclamation Fund, as defined in section 18(a) of the Surface Mining Conservation and Reclamation Act (52 P. S. § 1396.18(a)).
Authority The provisions of this § 86.186 issued under section 4.2(a) of the Surface Mining Conservation and Reclamation Act (52 P. S. § 1396.4b(a)).
Source The provisions of this § 86.186 adopted February 6, 1987, effective February 7, 1987, 17 Pa.B. 641.
Cross References The provisions of this § 86.187 issued under section 4.2(a) of the Surface Mining Conservation and Reclamation Act (52 P. S. § 1396.4b(a)); amended by sections 4(d) and (d.2) and 4.2(a) of the Surface Mining Conservation and Reclamation Act (52 P. S. § § 1396.4(d) and (d.2) and 1396.4b(a)); section 7 of the Bituminous Mine Subsidence and Land Conservation Act (52 P. S. § 1406.7); section 5 of The Clean Streams Law (35 P. S. § 691.5); section 3.2 of the Coal Refuse Disposal Control Act (52 P. S. § 30.53b); section 1920-A of The Administrative Code of 1929 (71 P. S. § 510-20); and PA. CONST. ART. 1, § 27.
Source The provisions of this § 86.187 adopted February 6, 1987, effective February 7, 1987, 17 Pa.B. 641; amended August 29, 2008, effective August 30, 2008, 38 Pa.B. 4742. Immediately preceding text appears at serial pages (313526) to (313527).
Cross References This section cited in 25 Pa. Code § 86.17 (relating to permit and reclamation fees); 25 Pa. Code § 86.145 (relating to Department responsibilities); 25 Pa. Code § 86.158 (relating to special terms and conditions for collateral bonds); 25 Pa. Code § 86.186 (relating to scope); 25 Pa. Code § 86.281 (relating to financial guarantees to insure reclamationgeneral); 25 Pa. Code § 86.284 (relating to forfeiture); 25 Pa. Code § 86.291 (relating to financial assurance for bond creditgeneral); and 25 Pa. Code § 86.295 (relating to forfeiture).
§ 86.188. Evaluation of bond forfeiture sites.
(a) After forfeiture of bond under § § 86.18086.182 and 86.185 (relating to scope; general; procedures; and preservation of remedies) has become final and the bond proceeds have been collected, the Department will evaluate the bond forfeiture site for reclamation purposes. The evaluation will consist of an onsite inspection by the Department and solicitation of information regarding the site and reclamation intention of the landowner and others determined by the Department to have information on, or an interest in, the site. The Department will provide to the landowner of the site, upon request, a copy of the completed site evaluation report.
(b) The Department will prioritize a bond forfeiture site according to the following categories, which are listed in decreasing order of severity of condition:
(1) Sites which present a significant and continuing hazard to human life by either their proximity to or impact on human populations.
(2) Sites which present a significant threat to health or safety, including actual or threatened loss of public or private water supplies.
(3) Sites which present a significant risk of damage to public or private property.
(4) Sites which are causing environmental degradation or pollution affecting the productive use of public or private land, or the reclamation of which would create significant environmental benefits.
(c) The Department, in selecting sites for reclamation under § 86.189(b)(1) (relating to reclamation of bond forfeiture sites), will consider the following factors:
(1) The severity of the conditions at the site.
(2) The potential for conditions at the site to deteriorate, including environmental quality, thus increasing the hazard to life, health, safety or property.
(3) The willingness of the landowner, or other person, to undertake the reclamation of the site under § 86.189(b)(2), (3) or (4), as evidenced by previous reclamation activity performed on the site or other indications of willingness to reclaim by the landowner or other person.
(4) The ability of the Department to gain adequate access to the site.
(5) The potential for remining of all or a portion of the site.
(6) The lack of participation of the landowner in the surface mining activities which created the conditions at the site.
(7) The potential for agricultural use or reforestation of the site.
(d) The Department will compile a list of sites for which forfeiture of bonds under § § 86.18086.182 and 86.185 has become final and bond proceeds have been collected. The list will be updated quarterly and will be available for review in the Departments district and central offices. The Department will publish quarterly in the Pennsylvania Bulletin notice of the availability of this list for review.
Authority The provisions of this § 86.188 issued under section 4.2(a) of the Surface Mining Conservation and Reclamation Act (52 P. S. § 1396.4b(a)); amended by sections 4(d) and (d.2) and 4.2(a) of the Surface Mining Conservation and Reclamation Act (52 P. S. § § 1396.4(d) and (d.2) and 1396.4b(a)); section 7 of the Bituminous Mine Subsidence and Land Conservation Act (52 P. S. § 1406.7); section 5 of The Clean Streams Law (35 P. S. § 691.5); section 3.2 of the Coal Refuse Disposal Control Act (52 P. S. § 30.53b); section 1920-A of The Administrative Code of 1929 (71 P. S. § 510-20); and PA. CONST. ART. 1, § 27.
Source The provisions of this § 86.188 adopted February 6, 1987, effective February 7, 1987, 17 Pa.B. 641; amended August 29, 2008, effective August 30, 2008, 38 Pa.B. 4742. Immediately preceding text appears at serial pages (313528) to (313529).
Cross References The provisions of this § 86.189 issued under section 4.2(a) of the Surface Mining Conservation and Reclamation Act (52 P. S. § 1396.4b(a)); amended by sections 4(d) and (d.2) and 4.2(a) of the Surface Mining Conservation and Reclamation Act (52 P. S. § § 1396.4(d) and (d.2) and 1396.4b(a)); section 7 of the Bituminous Mine Subsidence and Land Conservation Act (52 P. S. § 1406.7); section 5 of The Clean Streams Law (35 P. S. § 691.5); section 3.2 of the Coal Refuse Disposal Control Act (52 P. S. § 30.53b); section 1920-A of The Administrative Code of 1929 (71 P. S. § 510-20); and PA. CONST. ART. 1, § 27.
Source The provisions of this § 86.189 adopted February 6, 1987, effective February 7, 1987, 17 Pa.B. 641; amended August 29, 2008, effective August 30, 2008, 38 Pa.B. 4742. Immediately preceding text appears at serial pages (313529) to (313533).
Cross References This section cited in 25 Pa. Code § 86.145 (relating to Department responsibilities); 25 Pa. Code § 86.158 (relating to special terms and conditions for collateral bonds); 25 Pa. Code § 86.186 (relating to scope); 25 Pa. Code § 86.187 (relating to use of money); 25 Pa. Code § 86.188 (relating to evaluation of bond forfeiture sites); 25 Pa. Code § 86.281 (relating to financial guarantees to insure reclamationgeneral); 25 Pa. Code § 86.284 (relating to forfeiture); 25 Pa. Code § 86.291 (relating to financial assurance for bond creditgeneral); and 25 Pa. Code § 86.295 (relating to forfeiture).
§ 86.190. Sites where reclamation is unreasonable, unnecessary or impossible; excess funds.
(a) If the Department determines in the evaluation of a bond forfeiture site that completion of the approved reclamation plan of the licensed mine operator whose bonds were forfeited for the reclamation site or an alternative reclamation plan is unreasonable, unnecessary or physically impossible, the bond amount will be made available for expenditure from the Fund only to reclaim land and restore water supplies affected by surface mining operations for which the Department has forfeited bonds. The reasons justifying this determination include the following:
(1) The site has been repermitted and rebonded for mining, and reclamation of the site is a condition of the permit.
(2) The site has been otherwise reclaimed.
(b) Before a final determination under subsection (a), the Department will send written notice to the landowner of the Departments intention to remove restrictions on the expenditure of the forfeited bond amount.
(c) If the Department determines that the funds received from bonds covering the bond forfeiture site exceed the amount which is required to reclaim the bond forfeiture site, the excess funds will be made available for expenditure from the fund only to reclaim land and restore water supplies affected by surface mining operations for which the Department has forfeited bonds.
Authority The provisions of this § 86.190 issued under section 4.2(a) of the Surface Mining Conservation and Reclamation Act (52 P. S. § 1396.4b(a)); amended by sections 4(d) and (d.2) and 4.2(a) of the Surface Mining Conservation and Reclamation Act (52 P. S. § § 1396.4(d) and (d.2) and 1396.4b(a)); section 7 of the Bituminous Mine Subsidence and Land Conservation Act (52 P. S. § 1406.7); section 5 of The Clean Streams Law (35 P. S. § 691.5); section 3.2 of the Coal Refuse Disposal Control Act (52 P. S. § 30.53b); section 1920-A of The Administrative Code of 1929 (71 P. S. § 510-20); and PA. CONST. ART. 1, § 27.
Source The provisions of this § 86.190 adopted February 6, 1987, effective February 7, 1987, 17 Pa.B. 641; amended August 29, 2008, effective August 30, 2008, 38 Pa.B. 4742. Immediately preceding text appears at serial page (313533).
Cross References This section cited in 25 Pa. Code § 86.145 (relating to Department responsibilities); 25 Pa. Code § 86.158 (relating to special terms and conditions for collateral bonds); 25 Pa. Code § 86.186 (relating to scope); 25 Pa. Code § 86.187 (relating to use of money); 25 Pa. Code § 86.281 (relating to financial guarantees to insure reclamationgeneral); 25 Pa. Code § 86.284 (relating to forfeiture); and 25 Pa. Code § 86.295 (relating to forfeiture).
No part of the information on this site may be reproduced for profit or sold for profit.
This material has been drawn directly from the official Pennsylvania Code full text database. Due to the limitations of HTML or differences in display capabilities of different browsers, this version may differ slightly from the official printed version.