§ 1001.27. Subcontracting.

 (a)  A regional EMS council, which has received a contract from the Department, may receive the Department’s written approval to subcontract certain of its contractual duties to other entities as deemed necessary and appropriate for the proper execution of the contract with the Department.

 (b)  A subcontract may not be executed until the Department determines in writing that the subcontract is necessary and appropriate.

 (c)  Subcontractors will be paid on a cost reimbursement basis. The costs will be determined by the Department based on documentation submitted to the Department.

Source

   The provisions of this §  1001.27 amended October 13, 2000, effective October 14, 2000, 30 Pa.B. 5363. Immediately preceding text appears at serial page (247533).

Cross References

   This section cited in 28 Pa. Code §  1001.28 (relating to contracts with the Council).