52 Pa. Code § 75.31. Applicability.

INTERCONNECTION PROVISIONS


§ 75.31. Applicability.

 The interconnection procedures apply to customer-generators with small generator facilities that satisfy the following criteria:

   (1)  The electric nameplate capacity of the small generator facility is equal to or less than 5 MW.

   (2)  The small generator facility is not subject to the interconnection requirements of an RTO.

   (3)  The small generator facility is designed to operate in parallel with the electric distribution system.

Authority

   The provisions of this §  75.31 amended under 66 Pa.C.S. § §  501, 1501 and 2807(e); and sections 1648.7(a) and 1648.3(e)(2) of the Alternative Energy Portfolio Standards Act of 2004 (73 P.S. § §  1648.7(a) and 1648.3(e)(2)).

Source

   The provisions of this §  75.31 amended November 18, 2016, effective November 19, 2016, 46 Pa.B. 7277, 7448. Immediately preceding text appears at serial pages (342492) to (342493).

Cross References

   This section cited in 52 Pa. Code §  69.2101 (relating to statement of scope); 52 Pa. Code §  69.2102 (relating to statement of purpose); and 52 Pa. Code §  69.2104 (relating to interconnection application fees).



No part of the information on this site may be reproduced for profit or sold for profit.


This material has been drawn directly from the official Pennsylvania Code full text database. Due to the limitations of HTML or differences in display capabilities of different browsers, this version may differ slightly from the official printed version.