Pennsylvania Code & Bulletin
COMMONWEALTH OF PENNSYLVANIA

• No statutes or acts will be found at this website.

The Pennsylvania Code website reflects the Pennsylvania Code changes effective through 54 Pa.B. 1032 (February 24, 2024).

25 Pa. Code § 273.171. Gas monitoring and control plan.

PHASE II APPLICATION REQUIREMENTS—
GAS MANAGEMENT


§ 273.171. Gas monitoring and control plan.

 (a)  An application shall include a gas monitoring and control plan under §  273.292 (relating to gas control and monitoring). The plan shall include the following:

   (1)  A plan to monitor and record offsite gas migration and gas accumulation on and off the site, including structures.

   (2)  Designs for a gas control system, indicating the location and scheduling of construction, and the design of vents, barriers, collection pipes, manifolds or other control measures that will be put in place.

 (b)  If the applicant decides to conduct gas recovery, the application shall also include the following:

   (1)  Drawings and a narrative detailing the location and design of the proposed gas recovery system and the major onsite components of the system, which shall be consistent with §  273.293 (relating to gas recovery).

   (2)  Plans and designs to address special storage, transportation, processing, treatment or disposal measures anticipated or required in the management of the generated gases, condensates or other residues.

Cross References

   This section cited in 25 Pa. Code §  273.131 (relating to basic requirements); 25 Pa. Code §  273.292 (relating to gas control and monitoring); and 25 Pa. Code §  273.293 (relating to gas recovery).



No part of the information on this site may be reproduced for profit or sold for profit.


This material has been drawn directly from the official Pennsylvania Code full text database. Due to the limitations of HTML or differences in display capabilities of different browsers, this version may differ slightly from the official printed version.