25 Pa. Code § 87.152. Revegetation: seedbed preparation.

§ 87.152. Revegetation: seedbed preparation.

 (a)  The soil surface shall be prepared by disking or harrowing. If soil conditions or steep slopes prohibit these practices, the soil surface shall be scarified by any mechanical method which will loosen the surface material. Scarification will not be required if seeding is done immediately following final grading when the soil is still loose.

 (b)  Disking or harrowing shall be accomplished following or along the contours of all slopes.

 (c)  Topsoil shall be disked or harrowed to a depth of at least three inches prior to seeding.

Source

   The provisions of this §  87.152 adopted December 19, 1980, 10 Pa.B. 4789, effective July 31, 1982, 12 Pa.B. 2382; amended July 30, 1982, 12 Pa.B. 2473, effective July 31, 1982, 12 Pa.B. 2382.

Cross References

   This section cited in 25 Pa. Code §  87.68 (relating to reclamation information); 25 Pa. Code §  87.100 (relating to topsoil: nutrients and soil amendments); 25 Pa. Code §  87.104 (relating to stream channel diversions); 25 Pa. Code §  87.108 (relating to hydrologic balance: sedimentation ponds); and 25 Pa. Code §  87.138 (relating to protection of fish, wildlife and related environmental values).